Scottish council takes court action over faulty leisure complex
Local Scottish authority Dumfries and Galloway Council will take court action against contractor Kier Northern over a number of problems with the DG One leisure centre, which opened in 2008 at a cost of £17m.
A detailed report by independent technical experts found the cost of addressing defects in the gym, games hall, bar, swimming pool and changing village would total £3.7m.
At its policy and resources committee meeting on 22 January the council voted to take court action to recover £6m for remedial works and other reasonable costs and losses.
Work will begin January 2014, with dryside improvements expected to take four months and the wetside facilities taking 13 months.
Councillor Ivor Hyslop said he would be receiving a number of reports in the coming months detailing how issues with the building will be dealt with.
"We are all extremely disappointed and frustrated with the situation with DG One," he said.
When the leisure complex opened in May 2008, it was eight months behind schedule, which the council received liquidation damages for and attributed to slow progress by Kier.

Membership Advisor
Recreation Assistant/Lifeguard (NPLQ required)
Team Leader
General Manager
General Manager
Swim Manager
Membership Advisor
Sports Coach
Sports Coach
Swim Teacher
Party Leader
Group Exercise Instructor - Aqua
Membership Advisor
Swim Teacher
Swim Teacher
Activity and Wellbeing Instructor
Operations Manager - Brentwood School Enterprises
Swim Teacher
GP Exercise Referral Instructor
Duty Manager
Catalogue Gallery
Company profile
Directory
Featured Supplier
Property & Tenders
Company: Lee Valley Regional Park Authority
Company: Newmark
Company: EiA Real Estate
Company: Savills
Company: University of Oxford